New wedding venue at Laggan Outdoor looking good!

This £2m development is being delivered on a 28 week programme. We have used our offsite manufacturing facilities to achieve this by concurrently building on site whilst making components and sub assemblies off site in our workshops, enabling these components to be delivered as and when they are required. These components include all the structural steelwork to the main frame, timber frames, roof structures, external cladding, internal timber cladding to steelwork, various furniture fit out items, finishing joiner work and a bar. This strategy has enabled us to meet the demanding programme.